The bid is ready for signature. Sales wants flexibility to absorb customer requests. Operations wants contractor cover if key hires arrive late. Delivery wants room for extra supervision during a slower start.
All three requests may be reasonable. A healthy margin on the pricing sheet does not tell you how much room the company has to grant them.
The board’s minimum sets a tighter limit
Consider a hypothetical regional engineering firm. It is bidding for a year-long, $12 million fixed-price contract, with planned costs of $10.2 million and a 15% margin.
This firm’s board has set a minimum margin of 9% for any contract of this size. That leaves $720,000 between the planned profit and the board’s minimum.
Sales, operations and delivery each want discretion to meet a different cost. Each request is judged against the original margin, using separate estimates with no expense counted twice.
The firm’s existing senior engineers are committed to other contracts. Its cover estimate therefore assumes buying the required skills rather than moving staff across:
- Temporary cover for late senior engineers would cost $250,000 more than employing the planned hires.
- Customer additions accepted without an extra charge would cost $300,000 to deliver.
- Extra supervision and rework during a slower start would add $350,000 on the original scope.
Any two of those costs fit within the $720,000 headroom. Together, they consume $900,000 and reduce the contract margin to 7.5%, below the board’s minimum.
This contract is worth a fifth of the firm’s annual revenue. The choice warrants a leadership decision about the return and risk of the whole commitment.
Customer flexibility belongs in the price
Sales’ proposed flexibility is part of the offer. Accepting additional work without a corresponding fee increase would give the customer something of value, just as a lower price would. That concession belongs in the negotiation over what the contract includes.
If the firm already expects to incur some of these costs, those amounts belong in the delivery budget. Calling an expected expense a contingency would overstate the starting margin. A reserve covers uncertainty around the estimate. Expenses left out of the estimate belong in the estimate.
A reserve would give this firm a way to allocate its $720,000 of headroom. It would not create more room above the board’s minimum. Using it to pay for contractors would still reduce the profit available to absorb the other costs.
The alternatives change the agreement itself. A higher fee could pay for some of the exposure, while clearer limits on included work could make customer additions chargeable. A later start could reduce the need for temporary cover if the customer accepts the timing.
The negotiation could reflect what the customer values most. A fixed start date might be paired with tighter scope; more freedom to change requirements might come with a longer delivery window.
The customer might reject those changes. Protecting the return could cost the firm the contract, so the leadership choice includes the value of winning at the present terms.
If the customer insists on the original price, scope and date, the board could accept a lower margin for this contract or decline the work. Accepting it would be a deliberate decision about how much uncertainty the owners are willing to carry.
AI should challenge the links between costs
Use AI to propose connected downside cases from staffing plans, delivery dates and contract terms. A late engineering hire could affect both temporary cover and supervision costs. Those links belong in the approval discussion before the price is agreed.
The suggestions do not establish the likelihood or cost of those events. Those ranges need to come from the firm’s delivery estimates and agreed contract terms.
Settle the terms while there is still a choice
Before signature, the firm can still change the offer. Asking the customer for a higher fee after committing could leave it with fewer options than negotiating the concession now.
The example shows what happens if all three overruns land together. How likely that is remains a judgment for the people approving the bid.
Resolve the exposure before signature: price it, limit it in the contract, or accept it knowingly.